Philly Fixed a Melted Highway in 12 Days

A tanker fire brought down part of Philadelphia's I-95, but crews had traffic moving again just 12 days later. The contrast with years-long construction timelines is at the heart of Vox's “Philly Fixed a Melted Interstate in 12 Days. Why Does Everything Else Take So Long?” Norm Van Eeden Petersman explores that contrast with construction lawyer Michael Dieleman and Strong Towns chief technical advisor Edward Erfurt, who bring different experiences working on major public projects. They consider how emergency authority sped up the project and whether cities could remove some of that friction without sacrificing the safeguards that protect public money.

Norm Van Eeden Petersman  0:19

In June of 2023, a tanker truck caught fire beneath a highway, Interstate 95 in Philadelphia. The fire was actually so intense that a section of one of America's busiest highways collapsed. It was a disaster, and yet just 12 days later, traffic was moving again. Welcome, folks, to Upzoned, where we take an article from the news, and we talk about it, and think about what it has to say about what's going on now, but also what we should be thinking about in the longer term.

And if we think of that disaster on the highway, it's quite striking to think in 12 days you can reopen a completely collapsed interstate. At the same time, in communities all across North America. It can take months or even years to get a sidewalk built, a curb cut done, an intersection redesigned, or even a small housing project approved. And so the question is, what changes when something becomes an emergency?

And should we make everything an emergency in order to make it happen quickly? Because when our ordered systems break down and we need to adapt rapidly, what does that reveal about how we've organized sort of ordinary work of building and maintaining our communities? I'm excited to be able to welcome today my first conversation partner is my good friend Michael Dieleman, a Strong Towns member who is also a construction lawyer with Aecon, one of Canada's largest infrastructure companies.

Michael works behind the scenes on the complex contracts and negotiations that make these major infrastructure projects possible. And so, Michael, welcome to Upzoned for the first time.

Michael Dieleman  1:51

Good afternoon. Thanks for having me.

Norm Van Eeden Petersman  1:53

Yeah, great. And back again, I trust with more insight than ever is Edward Erfurt, our chief technical advisor at Strong Towns, in his work with cities large and small, Edward has had a hand in moving contracts and especially projects over the finish line, and also witnessed firsthand those bottlenecks that invariably snarl even the best of intentions in this process. And so, Edward, welcome back to your regular seat on the podcast.

Edward Erfurt  2:18

Thanks, Norm. It's always a pleasure to be here.

Norm Van Eeden Petersman  2:21

Yeah, fantastic. Well, the article that we want to talk about is in Vox by infrastructure reporter, which that's an amazing job if you can get it. Sarah Hershlander published November 12 called "Philly Fixed a Melted Interstate in 12 Days." Why does everything else take so long? It's a fantastic long form article. It will be linked in the show notes, and I would definitely encourage you to go and check it out because that response to the collapse was quite telling in a lot of ways.

That tanker truck had actually freshly cooked the concrete, and then that concrete fell apart, leaving the highway first with a demolition problem. They had to get rid of the waste, and then they had to figure out how to fix it so that way vehicles could start to travel over this span. State officials, when they first looked at it, said, "Oh, it's going to be weeks or potentially much longer." Instead, they reopened the highway on a temporary roadway just 12 days later.

And in this piece, Sarah explores how that happened. They had emergency authority. They expedited the contracting. They had round-the-clock construction, and they had readily available materials. And crucially, their decision makers were some of them who were even just living on site in a trailer were allowed to resolve problems almost immediately. and it's worth reading because it goes beyond just the remarkable construction speed or how quickly you can build something.

We know that we can build things quickly, but it asks why so many ordinary infrastructure projects struggle to make progress when our institutions have demonstrated that they actually are at times capable of doing things quickly. And for anyone in our audience who's ever played SimCity or Cities: Skylines, and what a delight it is to use the full powers of your godlike ability to hit the pause button, rework a highway, and then resume play and have everything just reoriented itself to your new design. I'd say this has got to be the closest real life analog available to be able to see this happen just in 12 days.

So that's where I want to start today's conversation, Michael. I bet none of your projects at Aecon have finished in 12 days. So, what kind of envy did you experience? But also, what did you make of the author's conclusion that if we want to fix more highways, build more train lines, or paint more bike lanes more quickly, it will need we need to get better at knowing when to break our rules more often, not only when there's an emergency.

In fact, it may be time to rewrite some of them altogether. Would love your take on that conclusion.

Michael Dieleman  4:51

Yeah, that's a very it's a very interesting point. I mean, 12 days is a fantastically short duration to do anything. In the world of emergency, though things are always different and things can go very quickly, especially when we're removing and replacing something that already existed. I think in any situation when we talk about the timeliness of fixing something, fixing presumes it was already there.

Whereas a lot of times, to the extent that we conflate how long it takes to fix something in emergency, as opposed to what it takes to do something new, those are very different processes and very different. There's a very different process for just getting buy-in to do something new, as opposed to fixing something that already existed. But it's an interesting point of like contract models are a key part of how you do things, and each of them, all contract models are geared towards achieving certain things, and a lot of the more, shall we say, modern models are an attempt to better align the interests of the taxpayer, the public, with contractors, or rather, align the interests of contractors with those that already exist in the public, if you will.

And in that process, you're also looking at timeliness is a big part of that. And some models are. I mean, I'm going into the weeds here, but they're they can be more responsive. And it's always a question of what are you trying to solve for? we don't generally solve for expedience in a very short timeline. It's often much more important in construction projects that we don't make mistakes, and that we have buy-in.

And by mistakes, I mean there's a lot of things that have to go to build a complicated, bridge structure, overpass, a water treatment plant, piping, all kinds of things that have to be planned. I would say our system is designed much more to ensuring that we don't have to we do it the first time because there's so many resources that are pulled together to do it, and that means that it's it's like the old adage of measure twice and cut once, but now you apply that to a construction project worth hundreds of millions of dollars. So the 12 days is interesting to me, but they broke so many rules and they were allowed to do things in ways that were that were usually just not allowed to do in construction, but many other jurisdictions have examples of emergencies where they were able to respond very quickly.

So it is impressive to me, but I don't know if it provides much of a model for other scenarios than similar scenarios where something disastrous has happened, and we need to get an item back in service very quickly.

Norm Van Eeden Petersman  7:47

Yeah, and Edward, the piece quotes the project latest thing as the example proved getting things done can become contagious. And he said, I keep getting calls from people saying, hey, can you do this for us, or what advice do you have for us? But, but is that the lesson to be drawn? As Michael has rightly said, not everything fits this bill. But what were some of the takeaways that you had from the article?

Edward Erfurt  8:10

Yeah, well, we have to recognize that in all of these types of highway and street projects, especially when it's federal money, money, the feedback loop on that is about the size of the circumference of the Earth via the path around Pluto. I mean, it is like yes, there's a feedback loop, but it is really, really long. What I found here with this project, and there have been a couple of these in recent memory of where there's been a catastrophic failure, and we've we've asked for these kind of extraordinary things, and we all describe this as kind of a miracle that we were able to do this stuff.

But in this case, speed was a choice; it wasn't really a miracle. The emergency declaration gave us the ability to move a little bit faster by cutting out many of the steps that would be required. I looked up to see what a standard highway project like this timeline would be, and nobody wants to admit it. But it's somewhere between seven and eight years, so it went from seven and eight years to 12 days.

They were fortunate because they're in an area of the country that actually have contractors readily available for this work, so they kind of migrated from one other project that, again, in their feedback loop, had a long, long tail they could go and like pull off and go there. They also, when we think about all of the systems we have in place, why does it take so long in that feedback loop, it has to do with making sure that we have all the appropriate buy-in when we are using federal money. So, federal government has this huge apparatus of checks and balances to make sure all the money is being used properly.

It's maddening. Of the bureaucracy there, but when you take that out and you say, "Okay, we're not going to do all those checks. We have the check is the emergency. We're going to do that. We can really remove a lot of that friction and reduce those feedback loops." So, when you look at a project like this, I would be highly frustrated if I'm working on the city on any other project, and we couldn't do it.

I won't say 12 days. Let's just say 24, 30 days. Like, could we do a project like this in 30 days in the city, and everybody would laugh at that? But I think on a thing like this, why one we shouldn't have to wait for catastrophic failure for this type of expedience, and then two we should really question what are all the things in that are taking a project this long to get through to fruition.

Norm Van Eeden Petersman  11:00

Well, it's like those astronauts golf game, really good and impressive on the moon. The trouble was like the resumption of gravity kind of ruined it for the rest of them, and I think that there's an element of that. And if I were to sum it up, I think there are several starting points on this piece that I think we can agree on. That like we are against fraud, and so public money does demand public accountability, Edward.

You're nodding to that in the context of like federal rules. Although I would say, if I have to walk for four days through a street that's full of pickpockets versus four minutes, the likelihood of me being pickpocked on pickpocketed on my way is much lower on that quick, brief sort of stint rather than that long journey in which there's always that risk of being defrauded or taken away as you go, but like we need these safeguards against corruption to maintain public trust and to maintain, I think, standards of human decency. But in addition to being against fraud, we're against waste.

But waste isn't just money being spent inefficiently, maybe overspending on steel girders. It's also about so often we end up building things that we don't need, maintaining things that we can't afford, or even spending years going through processes that add little value. For example, I would imagine one of the things that was waived for this project was a noise study and an environmental impact study.

Neither of them in that context were necessary because the same thing was being put back, and yet a lot of our contracts, whenever we bring them up for consideration or projects come forward, it's all right. You have to go through this whole suite of requirements as we go through, and so I think that this is a key part of it that like we should have safeguards, but not ones that are maximally designed to have procedural complexity. Regulations and oversight matter, but if the burden that they impose is so extreme to the risk that they're intended to manage, we need to be cutting away at that because our communities need to be able to adapt without crisis.

I think this is maybe that core element. It shouldn't take a fire. It shouldn't take a collapse for us to do the things that we know we should responsibly do. A emergency declaration should only be needed for these types of emergencies. But sometimes you're like, man, I really want to just get some kind of version of a declaration before we can take this on.

And then the last point that I would make is like I need to be pragmatic about the world as it exists. I want in a in a strong towns world, everybody's we've got locally led, locally funded projects that everybody in the community is participating in. We don't have consortiums led by Spanish construction giants that are underbidding our local contractors because of World Trade Organization rules, and then at the same time not delivering, and everything just ends up in court.

I'm speaking real examples here, but instead, when we when we work at this, we have to deal with these limitations as they exist in our places. And so, I like the challenge of this. How could we actually speed things up, Michael. Do you have some thoughts on like how would we move projects along more rapidly? You said at the table as the representative of the construction side, saying we could start tomorrow, and yet like so often, tomorrow is a long time coming.

Michael Dieleman  14:17

Yeah, that is a that's a really big question. I think one of the key things when we talk about feedback loops is that there are different types of feedback loops, and many feedback loops are actually really useful things. I think when you think about construction, is still very project management e, as opposed to manufacturing things, and as you increase the, and this is not so much the amount of positive feedback loops as the fact that they exist and the return period for them.

I think a lot of times when we think about vehicles and cell phones and things like that. they have a built-in feedback loop where there's just incremental change every year, and then they have customer feedback and they make additional change. and we're used to that, and we as consumers get used to this idea that certain things that we buy, we buy them every couple of years, and we expect them to be better every couple of years, and that's built into that product. we don't really have a very good way of doing that when it comes to public infrastructure, but yet that's also a very important thing I think for public infrastructure. So to the extent that if you look at maintenance contracts for highways, usually they're very large areas and they're set up in such a way that you bid on them, and they last for several years.

And it's hard to like the governments usually try to set them up in a way that you actually can change bidders and you can introduce competition. But there's such a huge barrier to entry with the capital, and how do you deal with that? Because what you fundamentally want is you want a contractor that is responsive to the needs of the community to repair infrastructure, and in order to do that, you need to have a base of workers that are able to operate the machinery and the equipment, and to do that, people are people at the end of the day that they want to know that there's a certain amount of long term. stability in an industry.

So to wrap this all around and come back to the point of what do I think could be changed to improve things is if government could provide government is itself a stable organization, but the way in which it interacts with industry is not always stable, and to the extent that you could say, instead of having one, two, three projects that are coming out at different times and a number of projects that are like they try to, and governments try to, develop a pipeline. But if you could have a pipeline that would be mapped out over a longer period of time, and you could have infrastructure work released in packages at set times and regular intervals. And good like there's a lot of variability in the entire industry.

But to the extent that you could provide enough certainty to industry of when work was coming out and how much work was coming out, that you could have a base of people contractors available to do your work, and that you can get a return period on whether or not that work goes well and whether or not that work is responsive to the needs. That is useful enough that the same individuals that are bidding follow-on work can fold that in. There's a belief, or wrong, in the world of project management, that almost any team is hard to keep intact for a period of more than three to four years.

You'll obviously have a lot more stability, and as generations change, I think you see even less stability in certain project management teams. but I imagine across a lot of individuals and organizations that you work with, that you'll see a huge amount of turnover, and that represents a huge amount of knowledge that is lost. And that feedback loop, if the feedback loop is too long in order to impact the people that made the decisions that originally resulted in the work, it's not a very useful feedback loop. So, where am I getting to with this?

I think that the point is, if you can set up a situation in which the objectives are known at an early point in time, the timeline is known, and you set up your work in such a way that you are effectively developing options and alternatives. Say you're a municipality, that you have five overpasses that have to be done in the next five years. you could choose to push, and this is where federal funding comes back into it. A lot of times you'll try to bundle those, and you'll try to get them in line with funding.

But in terms of stability and getting the best bang for your buck, you're probably better off to do something like I'm going to award one per year for the next five years, and I expect each of these projects to take 18 months to two and a half years, and then you'll get a number of bidders, and the wedding bidder will come into the next one, and you'll have this overlap where you're probably likely to get market pricing that most reflects the actual cost of the work, which hopefully is better for the taxpayer to the extent that nobody's carrying undue contingency, extra high pricing, and also nobody's taking a bath on the work, right? Like government needs to know that contractors are not charitable enterprises.

I think government knows that, but that you have to be able to allow the industry to make some money, and I think government knows. But if you throw too much risk at a contractor and things go wrong, that's not good for government either. And that goes back to the issue of claims, right? Is you're trying to find this balance of claims and feedback and allowing people to make decisions about their lives, and now applying that to huge construction projects or small construction projects, for that matter.

Norm Van Eeden Petersman  20:24

Yeah. Well, what you said about the four years of keeping a team together, and then beyond that, it starts to peter out. I think that's a really interesting element of it, as to whether or not speed is actually like one of the ways that you overcome it. In the article, it says they all of the participants, the on-site crew said we didn't want to be the one that slowed down progress.

Everybody felt like they were part of a play and wanted to make sure they played their part well. I think that there's an interesting layer that maybe we're actually just dealing with a with a human resources problem that the fire needs to be there or the energy and the readiness. I'm thinking of Bob's backhoe service would never have gotten a contract for this type for any of the parts of this project, except for the fact that the on-site supervisor says, "Do does anyone know a guy we need to move the footings for whatever we've just worked on?

Go!" And all of a sudden, your locals actually get brought in that way. Edward, maybe I mean this is love your reflections, but also I'm curious in your experience in municipalities. Did you ever see like requests for proposals going out? And certainly, I've seen it in my community where they get torqued or sort of twisted to try to get the preferred outcome.

But even then, that never seems to quite get it. That Bob's backhoe service actually gets a cut of the work. We have it with our garbage contract that every whenever it comes up for renewal, our city staff do everything in their power to make sure they keep the contractor, who I'm quite happy with. I'm glad they do. But there's a couple of low bidders that are basically trolling around Canada looking for these projects that they can come in on.

They've got terrible reputations. They never seem to meet their quality performance standards, and yet they always seem to hoover up new contracts. That seems like exactly the type of situation that results in highway projects that go on and on and on and on and on. municipal infrastructure projects that just never seem to like make it to the finish line without huge overages and contract disputes.

Edward Erfurt  22:16

There is an entire I'm going to call it a game because that's probably the best way to describe it: There's an entire game when it comes to contracting. So, we in the states, the way that our federal program works, the federal Department of Transportation disperses federal funds to our local state departments of transportation, and they have to account for all of that money with auditing, they then have the ability to go and disperse that down to a local level to do localized projects. So you have all these layers that are going to making sure.

Let's just look on the construction side before we do anything else. We'll just kind of back engineer that. When we finally have figured out the design we want and how we want to do it, at the very end, after years of work, we now are going to the construction side. So we've dealt the details out on this. Now the details and the materials that have been chosen were chosen two years ago or three years ago, because that's how long it takes for these engineering pieces to go forward.

They're in standards that have been set up by our state DOTS and our local jurisdictions that could go back even further. So there is not the innovation in these sorts of projects. We need to have a bit of predictability to it. And then we have on the contracting. There is for construction. We're asking for the bids for the lowest bid of the qualified team.

So it's not just the lowest number, but it also have to have some qualifications. When you look at the bid scoring sheets, depending on what type of funding source, there are other dials that are added in that deal with equity, veteran preferred, women-owned businesses. There are certain groups that get different scoring points to move up through that system.

So, when you look at all of that in that piece, we've got a scoring system that people are working towards the system, not to the construction. And then, of course, the companies that we see that would come forward, there are really, really good groups that are great at putting together bid packages, but they have a they don't have a single person with a hard hat in the office. So you have these corporations that are really good; they meet all the federal pieces, but they sub out every other aspect of the project.

But they've gotten that proposal there, so. So when we get to that, there are all of these layers, and again, that well intentioned in how this is set up, we want to be sure our tax dollars are well spent, but they lead to unintended consequences, and it will take decades to change all of those purchasing components to it, which is just for me, it's really frustrating, and I think when people see these projects come in, but even on this Philadelphia project, it amazes me they had the materials they needed because typically, what has been engineered out, every bridge is unique, every span is different. The if you go to the bridge company and say, "Okay, we need girders for a 60-foot span," you're put in the queue of the factory of every other group there.

Then once they manufacture it, you just can't like put a 60-foot girder on the back of a pickup truck and drive it to your job site. You've got to coordinate all of the logistics of getting that there, and then on a lot of these projects, these teams, as Michael shared, they're they're always changing. There's a diversity in those that are changing out.

Many of the construction jobs that we would see here locally, the subs that were coming from it and the labor were coming from far off places. We did we didn't have. I mean, how many highway projects could you have in your municipality in the next four or five years? you're getting one or two of these. So the specialist that knows how to put up lighting, or the person knows how to do the center guardrail work.

Those are all coming from other places that are rotating as specialists around the country to do all of that stuff. So, yeah, on the construction side, there is just on the building component of it. There's an enormous amount of logistics that go into place,

Norm Van Eeden Petersman  27:00

and that's if everything, if every drawing's if every piece of material comes in, it's correct. That everything's been installed properly. That the inspector was available that day, or there, there's not rain or snow. That those types of things on roadway projects. I think this in Pennsylvania would be a much different experience if this occurred in January in Pennsylvania than when it actually occurred.

Well, and actually, this totally connects, Michael. I'm going to ask you about the Pattullo Bridge project and talk about as much as you can legally. But this was a project to replace a large bridge across from New Westminster to Surrey in British Columbia, and the project missed several important deadlines. One is when you can do work in the river really matters, and so there's salmon that need to be able to pass through.

And so, because of delays on the environmental side as well as the archeological side, the project missed by a year its opportunity to start working in the water, and there was also the fascinating element when we had an atmospheric river come and take out a whole bunch of highway spans in our connections between British Columbia and the rest of Canada. Correct me if I'm wrong, but I believe like steel from your project was not stolen, but seconded to the project to basically build these repaired bridges. Here's your just a little bit more about that because it feels like another example where, on the one hand, you had a project that was just like slow and trundling along, and then missed a major deadline and just had to push everything back by a year with all of the costs that come along with that.

Whereas if there had been that urgency, you don't miss deadlines when everything is frantic in that same way. And then even just the interesting way in which they said, "Hey, all the steel is now potentially at risk of just being seconded to this project."

Michael Dieleman  28:55

Yeah, that's that's a number of things there. I mean, I'll start with Pattullo, and everything that I'll I'll say about Pattullo is already on the public record to the extent that I would characterize it the delays a little differently. Like they did fundamentally come down to a mixture of archeological issues and COVID issues. And a key thing to always understand in construction when you're building a large structure is that when you are planning, a lot of work has to happen in sequence.

So if you can't start, for example, say you're building a bridge and it has a whole bunch of piers, and you have bridge pier 12345, because of the crew that is actually installing the piles, for example, for those piers and the way that they work, you want that crew to work continuously. That you will intentionally delay starting pile like the first one until you're ready to finish all of them because it's very inefficient if you have to go from pier one, wait a bit, go to pier four, come back. Two go to three go to six and so forth.

So when you have delays at the outset of a project with like land issues, and this is a big thing that is relatively obvious, but also not spoken about a lot. I mean, maybe it is, but this idea that construction means we take the world as it is, and what we know about the world as it is only based on what we know at that point in time, and I know that's an obvious statement. But as soon as you start excavating and you start digging and you find things, invariably you find things you didn't expect to find, and some things are harder to deal with than other things.

If you find First Nations and indigenous artifacts. There's a complicated process for digging those up and preserving them. The same with dinosaur bones and things like that, right? So you can only plan to some extent what you're going to have when you start digging, and then to the extent that you encounter things in a larger area, that can impact the start date for everything.

So the way you can avoid that is you can spend a lot more money in what are called geotechnical investigations at the outset of a project. So Pattullo's challenge was, I think, from my perspective, that a lot of things happened a lot slower at the outset of the project, and then once you have a number of built-in delays, it's just very hard to recover from those because of the way in which we schedule things in order to still be efficient, right? It would be fantastically inefficient to continue with the same plan.

Like you can try to resequencing is what we call it in construction, where you change your schedule around to still match, but there are certain activities that are very, very expensive activities that you want to keep them lined up. So that's the Pattullo story, and there's other elements to it that are relatively complicated that I think are outside the scope of what I'm prepared.

Edward Erfurt  31:57

Yeah, but even that, like what Michael is also explaining, much of that is baked into the contract for construction. Every construction project we would do in the city, I would describe it as urban archeology, because we would never know what we would get. It didn't matter how many tests and how much engineering and mapping and geotechnical we've done.

We'd always end up finding something that was not where it was supposed to be. Then, with that, we have to pause and figure it out. Well, that now pushes our whole timeline out as we move forward. So that is part of the contracting process that occurs. Then. then you are working through something, and there's some sort of delay. you can't just switch teams midway through the project.

You have to work all the way through with the team that you chose. So if the pile team is not available because of a something at the beginning of the project, some sort of delay, you just can't find another team to do it. It that it's just part of that construction piece. I think with the Philadelphia project, with this bridge going out, it was a bridge and a very short section of roadway.

We're not talking about multiple miles. We're not talking about the entire section of I 95 through the downtown. I actually think the bigger project that came out of this was the diversion of all the traffic on I 95 in and around the site, like their detour route, and there was there were complications with that on the local level. But the fact is that we were able to maintain our federal highway system through Philadelphia without a total collapse of the system while they were doing these repairs, and the fact they were able to get this online within hours of this disaster, I find that like I have trust in the construction, even the ones that Norm you might think are a little unsavory and maybe aren't as skilled at this type of work.

I still have trust that at the end of the day, they're going to build out something that we are going to inspect that's going to meet our standards because we're not going to accept any of that stuff, and we're going to continue to make sure it gets done properly. But the temporary components, the stuff coming out immediately with cones and directional signs, that there is no in that emergency, there is no maintenance of travel plan that has been set out by an engineer. It is the police officers and a public works truck that are figuring out where we can put all of how many hundreds of 1000s of trips on a local street to get around one of the most critical pieces of infrastructure in the United States, and whatever wherever the path was, the first.

Night it was laid out, they just rolled with it, and I think that for me is the like an even bigger lesson in this project that we have the capability to do that. And it, I know we're in an environment where everybody wants to put shade on public sector folks, or they want to say how long it takes to get a project done. The fact that this was put together just shows like that was not something that night on a white horse rolled into town.

Those are the folks that are on the ground every day and continue to work in that city that are able to make this stuff happen, and when I look at these things, knowing what we can do, again, I'm not going to put the pressure on that we're going to do every project in 12 days, but I would start to figure out what are the things we were able to do that we didn't have to wait for money, we didn't have to wait for permission for, that we could work as a city to go repeat that on the other needs that we have on all of our roadways.

Norm Van Eeden Petersman  36:09

Yeah, totally. I mean, there's then maybe the test is if it's smaller than this overpass, move quickly, or. and this is the challenge that sometimes we see it that we will wait to dig up eight blocks of a city street, of city streets in order to do some large project rather than doing it block by block by block. Even though residents, if you ask them what would you prefer, they're like, please just do like one block at a time.

We understand how that works. We would even be willing to like suffer through a slight surcharge in terms of what each would cost us, and I think it speaks to some of that like iteration, learning from the process. If you do one block at a time, you might be able to then stack up the learnings from that first block and make improvements on the second one.

Whereas if you're doing all of your pipe work and then all of your groundwork and then all of your sidewalk work, all of the pouring just becomes all of that stuff just becomes very standardized, and of course it goes to plan. But the moment you open the ground, you discover things that you didn't count on, and so I think that there's always that challenge. And as we try to say, like, how do we bring back more of our local determination of what we can do together with limited resources?

I think that there are important lessons in that the other element is something the size of a bridge like the Francis Scott Key Bridge in Baltimore they're planning construction to be completed by 2030 but that is that several life cycles in terms of construction teams that several like rounds of people exiting and new people rolling in being like all what are we working on again. Well, don't get me don't get me started

Edward Erfurt  37:43

on that because it's closed, and I've driven around the area. I'm not a local, but do we need it? I was amazed with the 95 work through Philadelphia. How long could the city go with that bridge being out? I. I think it could have gone further with it, but Norm, one of the things, one of the outcomes of these types of really onerous packages of trying to get the contractor in place and mobilizing, is that we're forced to do big projects, and when we would do these projects in the city, we also get this appetite of success and this like fever of construction.

All of the contracts I had the ability for us to do change orders. So once we locked in the unit pricing and we knew what things were, and we saved a little money here, we a little bit faster there. We, I don't know. I don't know what you would call us, but what we would end up doing is saying, "What more could we do? Could we could we extend the repaving another street?

Could we go and build that connection? Do a little bit more of the stormwater because we've locked in the prices and there's predictability to it, and we don't have to pay for additional mobilization. So when you have these really big projects, there's also this creeping out, and of course the contractors want all that work. They're not going to say no to it, but it also puts us at risk where we're going to be in continual construction all the way through a lifetime to get everything that we want done, because fundamentally it took us so many years to get the first bulldozer on site.

Yeah,

Michael Dieleman  39:31

yeah. I mean, change order is always a beautiful word to contractors in our phrase.

Norm Van Eeden Petersman  39:36

Yeah, that's that's what pays for your Christmas party. I don't know if I

Michael Dieleman  39:41

say that, but

Edward Erfurt  39:43

well, for cities, it's the it's the fixed price sheet in the bid package. Oh, now we know what every pipe costs, and we there's a project we worked on in the last municipality I was at where the contractor wanted the job, so. they kind of fudge the numbers. They know what it's going to take to do it, and there's certain things that they would lowball within the bid package because they're going to make it up on the other end.

And one of them had to do with sewer lines. They were half the price in their bid package than what we had at any other contractor because it was the one they were

Norm Van Eeden Petersman  40:21

gently used,

Edward Erfurt  40:22

yeah, yeah. Because it was like the one place they were just going to squeeze. I don't know if it was like the person doing the bids had to find a way to lower the number, and that's where they did it. So we leveraged that to try to get as much sewer as we could get in the ground at that price, because the cost unit in the sheet, so yeah, the there was a change order, but on the flip side, the change order was a real pain for this contractor because they were losing money on every foot of pipe they had to install.

I

Michael Dieleman  40:53

mean, you touched on another interesting point, Edward, and I think Norm did as well. We didn't use the buzzword of resilience, but in the case of Philadelphia and many other things in construction, one of the things that these emergencies show is: have we developed a transportation system? And this applies to municipalities and all kinds of other types of owners that have infrastructure.

Is what type of resilience have you built into your system, so that if part of it goes offline, what can you do? Like, to what extent had the I 75 been designed or developed in a way that it would be less likely that the whole thing could come out in one discrete section? Now, you're never going to be able to solve for all catastrophes, but from a and COVID taught us this as well, right?

To what extent do you have resilience in your supply chains and resilience in your contractor community, where you have more contractors and you keep enough pipeline of work that you have people available to bid on your work and to chase work, and you have a system in which you're better off as a municipality, to keep four or five contractors busy, a little less busy than to keep one contractor super busy over a period of time. And when it comes to even your network, don't to the extent you can avoid it. I mean, the interstate system is federal government, but to the extent you can have some amount of redundancy in the arteries of your city, are like a key part of minimizing the impact and also having detours available.

Norm had earlier spoke about this atmospheric river that came through British Columbia a number of years ago, and it wiped out a bunch of sections of the highway. One of the things that not everyone realized at the time is we were able to get that system online very quickly. In part because there were contractors working immediately adjacent to that area, and British Columbia has a very large logging industry.

And whenever you have a logging industry, you also have a side industry of Forest Service roads, and Forest Service roads are very quickly built roads that can handle a decently large amount of weight. And to the extent that expertise and temporary bridges existed, you have a system already in place that is able to quickly mobilize and provide emergency access to areas that don't otherwise have access. And it's like obviously you can't replicate that model in other areas very easily.

But what can you do so that from the beginning, people talk about you probably heard like safety by design, right? Where you away plan. I think it's a big part of like how street planning is. But to what extent can you also have resilience by design. I mean, I don't think I'm I'm breaking any eureka moments here and saying to what extent can we as taxpayers encourage our public owners and utilities to ensure they're already moving this direction.

But a 12 day bridge repair shouldn't be needed if you have done a good job of having a resilient infrastructure system,

Norm Van Eeden Petersman  44:04

yeah, yeah, you're you're a lot less vulnerable that way. and this is to me the interesting thing in like an Amish barn raising is that the Amish are like, hey, we're all we're going to ask of you is just like a brief portion of your time. We're going to all pool it together, and that will be the equivalent of like all of a sudden a Forest Service road is available that otherwise we would never have thought to use. It's like yeah, I'll go help Obadiah go build his barn, and then in that moment all of a sudden you get this groundswell of activity and it all comes together.

And interestingly, in the article it says after they installed a 24/7 live stream on site, so that way people could follow along, and the workers were becoming heroes. Their efforts were broadcast on the jumbotron of a Phillies game, and updates were going viral on TikTok. And people were visiting the site offering cookies and donuts. And to me, like there's this interesting way of like in the squeeze, you actually get these really interesting like secondary benefits.

That you might not have anticipated, and that to me is also why you feed the folks that came to help you raise your barn. You just give them a meal, but in return they have done something that it would have taken you a six months out of the field or much longer to be able to do it. Now I know that I don't want to get too nostalgic, but there's an element of like what there's an interesting way in which we profile a lot of these stories of communities just buckling down and getting it done.

That is feels really appealing, but actually I think is part of what we need to rewire into our systems. And so yes, for every change order where you've got a better deal on sewage pipes, that's the rarity compared to most of the time where it just is that struggle of oh here we go especially when provincial standards or state standards require us to go through hoops and hurdles that just don't feel like they're fit for purpose any longer and so this might be part of that awakening of hey we have some things that we simply can't afford to wait on and I think of this especially in the context of dilapidated local streets and the message that it sends in our community that we're not investing in places, our streets that, from a strong town's perspective, we say a street is a platform for building wealth.

It is, it is, it is an important conduit that needs to be connected to vibrant private investment. And if you degrade that conduit, the private investment suffers lags behind and has a massive economic consequence. If your community feels like there's no reason to invest in their properties, and then from that we then further degrade the Commonwealth.

And in this case, what was clear is I 95 or I always get the numbers mixed up. that highway has to open because the quick back of the math or back of the envelope math was all these trucks, all these trips, all of that economic activity cannot happen if this artery is severed. And so it's like we got to stop the bleeding, we got to go. But it's the slow bleed in our communities of the things that actually do degrade the overall well being of our places that I think at Strong Towns we're like we've got to address that hidden element of the crisis that we face, and so I know we're going to come to the down zone in just a moment.

But closing thoughts or ideas from each of you?

Edward Erfurt  47:13

Well, I think that it is a heroic effort to be able to get a project like this done in this short time frame, and 12 days may be kind of a miracle time to it. But what in the United States, when we put our minds together to do something, we can accomplish incredible things. I don't think it has. We have to wait for a big disaster like this for this stuff to work.

If I was in city management in Philadelphia or in the Pennsylvania DOT, I would be having my teams meeting round the clock now to figure out how we were able to accomplish every aspect of this, that all of this would work, and I would ask where are we getting bogged down to prevent that delivery on future projects? So maybe it's a 12 day, but maybe we could get the Pennsylvania Turnpike paved over next summer, as opposed to over the next 20 years of orange barrels down the Turnpike. So thinking in those types of senses, and anywhere that we could find the small things that we were that the city was able to do in support of the project, because clearly it's much easier to do a roadway project when you can shut off all the traffic versus having to flip lanes back and forth.

What are things that we could do to help that as a city to make sure that we'll be in a small amount of pain for a very short time versus this perpetual build out? That's the type of thing that is the lesson out of this that I think can apply to every department that is working within our public of ways.

Norm Van Eeden Petersman  49:03

Yeah, that's awesome, Michael.

Michael Dieleman  49:07

Yeah, I would I would develop that same idea a bit further to say that to what extent can you in whatever infrastructure you're developing plan that infrastructure so that there, and I almost want to abuse what Edward just said that you can have a perpetual system of construction, but that can be less disruptive. In the sense that if that there is always going to be some amount of work ongoing, and you plan it in such a way that work can always be occurring, and it can be much less disruptive, because because at the end of it, I think you actually do like a healthy community requires a certain amount of rehabilitation, new construction, all the time. And what people dislike the most, I think, is the people love to see new things being built.

I think I mean I'm probably inherently biased. And stating that they just don't like the disruption of it, and to the extent that you have a system that makes it easier to build things in a less disruptive way, I mean, we already do a lot more utilities where we can do trenchless excavation and things like that, but there are also other ways where if you plan your city in such a way that you can take overpasses in and out of service on a somewhat regular basis. Every overpass that's ever been built is going to have to be rebuilt at some point in time.

What have we done in our planning such that we're able to accommodate that? And can you plan the rehabilitation and the future development of your city in such a way that it is it's almost like are you building the house so it can be renovated or are you not? And that would be that'd be the my parting thought is to the extent that we are less adverse to just construction existing and more cognizant of what we can do to make that construction easier to accommodate, that could be a useful development, and also to make sure that everything we do, we do it in such a way that we are encouraging feedback loops to provide return periods that are useful, that the lessons can actually be employed, and the benefits received by the individuals that had to suffer through the first part of the feedback,

Norm Van Eeden Petersman  51:26

right? Yeah, the breakdown, all of those things. Yeah, and your comment makes me just think that any city public works department that doesn't have its own tree nursery, to me, is making a grave error because that you're going to need the trees, that you plan to plant them at some point, and yet we pay landscapers all the time to go to the nursery to pick out a tree that they have gone about the hard work of growing from a sapling into it.

Even though the actual work is just stick a stick in the ground, give it some water every so often, and watch it grow. And so cities that don't have it, I'm like, especially the ones that have sold them off, I don't understand the mechanism there, because we want to have these resources at the ready when they're needed, and the best time to plant that tree was years ago, and to make that possible. So on that front, let's pivot into the down zone because this is our opportunity to talk about what we are discovering in our communities that just is interesting to you.

And so I'll start just with a related article, actually, Seth Zarin, a couple of years ago, he's a Strong Towns member and contributor, wrote an article: "Do things need to burn for new things to grow?" It's a great piece. I'll make sure that it gets linked in the show notes and really asks the question: Were the fires in Chicago, in San Francisco, and other places were those actually necessary at the scale that they occurred, for the things that we now see and appreciate and admire, for that to become possible, or is there sort of a lesser version of clearing your forests with regular fires, sort of to further the analogy with the trees? So that's the one that I'm reading.

I went back and reread it and thought it was fantastic. Thought it would be my Upzoned item. Edward, over to you.

Edward Erfurt  53:02

Well, Seth can really take a room down. Let me just tell you with his writing. I'm going to go a little bit different direction to kind of give some insight of where my mind's at and what I like to do in my free time. I've been watching the series The Diplomat on Netflix. I'm a I'm a huge fan of it, and just at the beginning of the month, or sometimes the middle last month, that the new season came out, and I just I love all of these like political spy drama things because it is not that far from the reality on the ground, and I find it just really amazing.

So, if somebody is out there looking to binge on some drama and they want a little bit of government flair into a little spy craft, I would definitely recommend checking out The Diplomat.

Norm Van Eeden Petersman  53:58

When I've heard that, like if Pitt is to medical dramas what The Diplomat is to actual diplomacy. People feel like it's the closest thing to what the reality is a lot like. So yeah, that's a great recommendation, Michael. You've got the floor.

Michael Dieleman  54:12

Yeah, it's. I feel like mine is. It's going to make me sound like I am a much more intense person than I actually am. I'm currently working my way through a book called Extreme Ownership: How U. S. Navy SEALs Lead and Win by Jocko Willink and Leif Babin, and how does that apply to what we've talked about today? I think probably the interesting thing, and I'd recommend that book simply because what it does very well is it develops the idea which we all I think inherently know that in order to one of the easiest ways to improve society and improve things is to start by improving yourself because you can you can.

Improve yourself. Nobody is stopping you from improving yourself. And what are the lessons that you can take in terms of how to better work with other people and how to better communicate? There is there's a kid version. I think there's actually a movie that's just come out or about to come out, the Way of the Warrior Kid that I read with my kids, and I have four kids, and after that they suddenly were doing more push-ups and things like that.

But there's an interesting concept, and I don't want to sound like I'm a military hawk in saying this, but there is there is always I think value in that is applicable to the world of infrastructure. That if we can be disciplined in responsible ways, we can have better outcomes than if we're not disciplined. Which maybe is such a truism that is not valuable, but it's still a useful point to make.

I think.

Norm Van Eeden Petersman  56:00

Yeah. Oh, I feel like totally applies because we need to set ourselves up for the ability to be decisive rather than dithering our way into the problems that we face. Maybe that's my cynical take on the whole thing. It's been fantastic. Thanks for joining me on Upzoned today, both Edward and Michael. It's awesome to have the both of you. This is great.

Michael Dieleman  56:18

Thank you.

Norm Van Eeden Petersman  56:19

We'll have to do it again. All right. Take care, everyone. As and again, thanks for listening to the episode. Have a great rest of the week. Take care. This episode was produced by Strong Towns, a nonprofit movement for building financially resilient communities. If what you heard today matters to you, deepen your connection by becoming a Strong Towns member at strongtowns.org/membership.

‍